When can the Sprint Backlog be modified?

  1. At any time during a Sprint

  2. Only during Sprint Planning

  3. At the end of each Sprint

  4. Only with approval from the Product Owner

The correct answer is: At any time during a Sprint

The Sprint Backlog can indeed be modified at any time during a Sprint. This reflects the nature of Scrum as an adaptive framework that encourages responsiveness to change. As the team gains more insight into the work from the Sprint's progress, they can adjust their plans to ensure that they are delivering the highest value. For instance, if a team member identifies a more efficient approach or if new unforeseen issues arise, the team can adapt by adding or removing items from the Sprint Backlog. This flexibility reinforces collaboration within the team and allows for continuous improvement during the Sprint, aligning with the principles of Agile methodology. It's essential that the team maintains transparency and communicates these modifications to ensure everyone is aligned and aware of the current goals and tasks.